Opened the debate
The hospital is constructed mainly from reinforced autoclaved aerated concrete, which has significant structural deficiencies. Over 83% of the building, including the roof, uses this material, leading to frequent leaks and water pooling issues. The hospital experiences more leaks than any other in the country due to its flat roof design and wet climate. There are over 50,000 aerated concrete panels, making it the worst affected NHS trust asset. Structural failures have been identified with deflections approaching critical levels. Emergency funding of £15 million has already been approved, but the backlog maintenance is at £480 million, rendering removal or replacement financially unviable.