Key points

  • Southampton's port electrification projects face grid upgrade delays for at least another decade.
  • Helen Morgan inquired about Bute Energy's wind farm plan connecting to a non-existent substation.
  • Minister offered to meet Helen Morgan to discuss the wind farm and substation issues.

Topics (select to filter)

Questions & Answers

Context

Darren Paffey notes that Southampton's port electrification and decarbonisation projects are ready but cannot proceed due to a lack of national grid upgrades expected to take a decade. The Prime Minister previously highlighted that such delays drive up costs, reduce growth, and hinder Britain's progress.

Question

Southampton's port electrification and decarbonisation projects are ready to go, but we still cannot get the national grid upgrades that we need for at least another decade. The Prime Minister himself has said that this drives costs up, drags growth down and holds Britain back, so I really welcome the announcements about Great British Grid. Will the Minister say when GB Grid will be able to start filling those gaps that exist at the moment, and will he meet me and Southampton's businesses so that we can find a way forward and get good green growth in Southampton's postcodes?

Answer from Michael Shanks

My hon. Friend is absolutely right to highlight the point that the Prime Minister made about how critical it is to fix the fundamental problems with connecting to the grid. That is why we have announced that we have set up Great British Grid as part of Great British Energy. We have made substantial progress on reforming the queue, but we do have to build the grid after decades of under-investment. I am very happy to meet my hon. Friend to discuss this issue, and I am fairly confident that we can make sure that National Grid is part of that conversation as well.

Partly answered

Not addressed: Specific timeline for Great British Grid to start filling gaps was not provided

Was this summary accurate? Tell us

How accurate was this summary? (1 = poor, 5 = spot on)

Get updates like this by email
Context

Helen Morgan expresses concerns about a planned wind farm in mid-Wales connecting to a substation in North Shropshire that does not yet exist, raising questions about the appropriateness of the site and potential alternatives.

Question

Bute Energy is planning to build a big wind farm in mid-Wales, and it is going to connect that wind farm over 47 km of pylons into a substation in North Shropshire that does not yet exist. I found out on the National Energy System Operator's website that that substation is likely to be a 24 bay, 400 kV substation in a place with no substantial roads and a good amount of useful farmland. Will the Minister meet me to discuss the appropriateness of the site? I think it could go elsewhere, which would require a shorter run of pylons for Bute Energy. There are more appropriate places to build it than Lower Frankton.

Answer from Michael Shanks

I am very happy to meet the hon. Lady to discuss this issue, as I am always happy to meet Members from across the House. It is not for me as a Minister to decide the exact locations of substations, but I am happy to engage with her and to raise the issue with the relevant transmission owner.

Partly answered

Not addressed: Specific decision on substation location was not addressed