Energy Infrastructure Planning Projects
02 September 2026
Type
Written Ministerial Statement
Department
Department for Energy Security and Net Zero
TAGS
At a Glance
Issue Summary
The statement addresses an extension of the decision-making deadline for a solar farm application under the Planning Act 2008.
Action Requested
The Secretary of State has set a new deadline of 10 November 2026 for deciding the Botley West Solar Farm application, allowing for further consideration of information from the applicant.
Key Facts
- The application was made by Photovolt Development Partners (PVDP) on behalf of SolarFive Limited.
- The original statutory deadline was 10 September 2026.
- The new deadline for the decision is 10 November 2026.
- The extension allows for consideration of additional information from the applicant.
▸