Energy Infrastructure Planning Projects
12 May 2022
Type
Written Ministerial Statement
Department
Department for Business, Energy and Industrial Strategy
At a Glance
Issue Summary
This statement addresses a new deadline set by the Secretary of State for deciding an application under the Planning Act 2008.
Action Requested
The Secretary of State has decided to extend the decision-making period for the Sizewell C Nuclear Power Station application to no later than 8 July 2022, allowing sufficient time to consider additional information submitted by the applicant and interested parties.
Key Facts
- The application is made under the Planning Act 2008.
- NNB Generation Company (SZC) Limited seeks permission for a nuclear power station near Leiston in Suffolk.
- Original statutory deadline was 25 May 2022.
- New decision-making period ends on 8 July 2022.
▸