Electricity and Gas Transmission (Compensation) Bill - Sitting 1

25 January 2023

Proposing MP
Dundee East
Type
Public Bill Committee

At a Glance

Issue Summary

The statement discusses amendments to the Electricity and Gas Transmission (Compensation) Bill to clarify its scope for electricity-related land acquisition cases and ensure accessibility and enforceability of dispute resolution processes. The statement discusses the Electricity and Gas Transmission (Compensation) Bill, which aims to improve dispute resolution processes for land acquisitions related to electricity network infrastructure. The statement discusses the establishment of an alternative dispute resolution taskforce to address disputes between landowners and electricity network operators. The statement discusses amendments and new clauses for the Electricity and Gas Transmission (Compensation) Bill, focusing on alternative dispute resolution processes for electricity-related land acquisition cases.

Action Requested

The MP requests clarification on whether the Bill will apply to current, ongoing disputes not settled at the time of commencement, provides an update on the timeline for implementation, and confirms the applicability of the Bill in Scotland. The MP also asks the Minister to review the territorial extent of the Bill to include Northern Ireland.

Key Facts

  • Amendments aim to clarify the scope of the Bill for electricity-related cases.
  • Proposals must ensure accessibility without undue difficulty or expense.
  • Determinations reached through dispute resolution processes must be independent and enforceable.
  • The MP seeks assurance that current disputes will be covered by the Act.
  • The Bill seeks to address disputes arising from land acquisitions related to the electricity network infrastructure.
  • The amendments focus on improving dispute resolution processes by encouraging the use of alternative methods rather than immediate tribunal recourse.
  • A taskforce is proposed to generate ideas for dispute resolution options, which will cover ongoing disputes once implemented.
  • An alternative dispute resolution taskforce will be established to address disputes between landowners and electricity network operators.
  • The taskforce is expected to be established in 2023.
  • The Bill applies strictly to cases where a development consent order has been granted for electricity transmission infrastructure under the Planning Act 2008.
  • The Bill's short title has been amended to reflect its contents.
  • Clause 1 was disagreed to, and a new clause focusing on electricity-related cases was added.
  • A technical amendment changed the term 'applies' to 'extends' in clause 2.
  • Another amendment delayed commencement of the Act by two months after Royal Assent.