Issue Summary
This statement addresses an application for development consent under the Planning Act 2008 for a solar farm project in Lincolnshire, South Kesteven and Rutland.
Action Requested
The Secretary of State has set a new deadline of no later than 13 June 2024 to make a decision on the Mallard Pass Solar Farm application, ensuring there is sufficient time for review.
Key Facts
- The application was made by Mallard Pass Solar Farm Limited.
- The current statutory deadline was 16 May 2024.
- A new deadline of no later than 13 June 2024 has been set.
▸