Energy Infrastructure Planning Projects
09 January 2024
Type
Written Ministerial Statement
Department
Department for Energy Security and Net Zero
At a Glance
Issue Summary
This statement addresses an extension application for two offshore wind farms off the Norfolk Coast under the Planning Act 2008.
Action Requested
I have decided to set a new deadline of no later than 17 April 2024 for deciding this application, allowing sufficient time for further consideration and consultation.
Key Facts
- The application is made by Equinor New Energy Limited.
- The original statutory deadline was 17 January 2024.
- The new deadline set is no later than 17 April 2024.
▸