Energy Infrastructure Planning Projects

06 February 2025

Proposing MP
Rutherglen
Type
Written Ministerial Statement
Department
Department for Energy Security and Net Zero

At a Glance

Issue Summary

This statement addresses an extension of the statutory deadline for a decision on the Rampion 2 Offshore Wind Farm Extension Project.

Action Requested

I have set a new deadline of 4 April 2025 to allow time to request further information. This decision is without prejudice to the final outcome of granting or refusing development consent.

Key Facts

  • Application for development consent made by Rampion Extension Development Limited under the Planning Act 2008.
  • Original statutory deadline was 6 February 2025.
  • New deadline set for 4 April 2025.