House of Commons · Written Ministerial Statement

Energy Infrastructure Planning Projects

30 October 2025 · Department for Energy Security and Net Zero

Proposed by Martin McCluskey Lab Inverclyde and Renfrewshire West

Summarised by AI from the official record, so it can contain mistakes.

View on Parliament.uk

At a glance

Key points

  • The Secretary of State has extended the statutory deadline for a decision on H2 Teesside Limited's application for a blue hydrogen production facility.
  • The new deadline set by the Secretary of State is December 4th, 2025.
  • This extension allows for more thorough consideration of the application.

Issue summary

This statement addresses an extension of the statutory deadline for a decision on H2 Teesside Limited's application for a blue hydrogen production facility.

Action requested

The Secretary of State has set a new deadline of December 4th, 2025, to allow more time to consider the application thoroughly.

Key facts

  • The Planning Act 2008 requires a decision within three months after receiving the Examining Authority’s report.
  • The original statutory deadline for the H2 Teesside Limited application was October 30th, 2025.
  • A new deadline of December 4th, 2025 has been set.