Key points
- The Secretary of State extended the statutory deadline for a decision on the Five Estuaries Offshore Wind Farm project to 17 December 2025.
- The extension allows time to request and consider additional information needed for the application's evaluation.
- The decision aims to ensure comprehensive assessment of the project's impacts and feasibility.
Issue summary
This statement addresses an extension of the statutory deadline for a decision on the Five Estuaries Offshore Wind Farm project.
Action requested
The Secretary of State has set a new deadline of 17 December 2025, allowing time to request and consider additional information necessary for the application's evaluation.
Key facts
- Application made under the Planning Act 2008 by Five Estuaries Offshore Wind Farm Limited.
- Original statutory deadline was 17 September 2025.
- New deadline set for 17 December 2025.
- Extension allows time to request additional information and provide review opportunities.
▸