Energy Infrastructure Planning Projects

06 February 2025 · Department for Energy Security and Net Zero

Proposed by Michael Shanks Lab Rutherglen

Summarised by AI from the official record, so it can contain mistakes.

View on Parliament.uk

At a glance

Key points

  • The statutory deadline for a decision on the Rampion 2 Offshore Wind Farm Extension Project is extended.
  • A new deadline of 4 April 2025 is set to allow time to request further information.
  • This decision does not influence the final outcome regarding granting or refusing development consent.

Issue summary

This statement addresses an extension of the statutory deadline for a decision on the Rampion 2 Offshore Wind Farm Extension Project.

Action requested

I have set a new deadline of 4 April 2025 to allow time to request further information. This decision is without prejudice to the final outcome of granting or refusing development consent.

Key facts

  • Application for development consent made by Rampion Extension Development Limited under the Planning Act 2008.
  • Original statutory deadline was 6 February 2025.
  • New deadline set for 4 April 2025.