House of Commons · Written Ministerial Statement
Energy Infrastructure Planning Projects
06 February 2025 · Department for Energy Security and Net Zero
Proposed by Michael Shanks Lab Rutherglen
Summarised by AI from the official record, so it can contain mistakes.
At a glance
Key points
- The statutory deadline for a decision on the Rampion 2 Offshore Wind Farm Extension Project is extended.
- A new deadline of 4 April 2025 is set to allow time to request further information.
- This decision does not influence the final outcome regarding granting or refusing development consent.
Issue summary
This statement addresses an extension of the statutory deadline for a decision on the Rampion 2 Offshore Wind Farm Extension Project.
Action requested
I have set a new deadline of 4 April 2025 to allow time to request further information. This decision is without prejudice to the final outcome of granting or refusing development consent.
Key facts
- Application for development consent made by Rampion Extension Development Limited under the Planning Act 2008.
- Original statutory deadline was 6 February 2025.
- New deadline set for 4 April 2025.
▸