House of Commons · Written Ministerial Statement
Energy Infrastructure Planning Projects
07 March 2024 · Department for Energy Security and Net Zero
Proposed by Claire Coutinho Con East Surrey
Summarised by AI from the official record, so it can contain mistakes.
At a glance
Key points
- The Secretary of State has decided to set a new deadline of no later than 11 April 2024 for deciding the application.
- The new deadline extends beyond the original statutory deadline of 7 March 2024.
- The statement concerns an application for development consent for a solar energy project in West Suffolk and East Cambridgeshire.
Issue summary
This statement addresses an application for development consent under the Planning Act 2008 for a solar energy project in West Suffolk and East Cambridgeshire.
Action requested
The Secretary of State has decided to set a new deadline of no later than 11 April 2024 for deciding this application, extending beyond the original statutory deadline of 7 March 2024.
Key facts
- The application is made under the Planning Act 2008 by Sunnica Energy Farm.
- The current statutory deadline for decision is 7 March 2024.
- A new deadline has been set for no later than 11 April 2024.
▸