At a glance

Key points

  • The Secretary of State is extending the decision deadline for the A303 Amesbury to Berwick Down Development Consent Order application from 17 July 2020 to 13 November 2020.
  • The extension allows for further archaeological consultations within the Stonehenge World Heritage Site.
  • The Planning Act 2008 provides the legal framework for the decision-making process.

Issue summary

This statement addresses the extension of the deadline for a decision on the A303 Stonehenge application under the Planning Act 2008.

Action requested

The Secretary of State is extending the deadline for making a decision on the A303 Amesbury to Berwick Down Development Consent Order application from 17 July 2020 to 13 November 2020 to accommodate further archaeological consultations within the World Heritage Site.

Key facts

  • The Planning Act 2008 requires a decision within 3 months of receiving the Examining Authority’s report.
  • The deadline was previously extended from 2 April 2020 to 17 July 2020 for further work.
  • A recent archaeological find necessitates an additional extension to 13 November 2020.