Energy Infrastructure Planning Projects
17 October 2024
Type
Written Ministerial Statement
Department
Department for Energy Security and Net Zero
At a Glance
Issue Summary
This statement addresses an extension of the deadline for a decision on the North Lincolnshire Green Energy Park Limited's application under the Planning Act 2008.
Action Requested
The Secretary of State has set a new deadline of no later than 14 March 2025 to decide this application, allowing sufficient time for consideration and consultation with Interested Parties regarding a Residual Waste Infrastructure Capacity Note.
Key Facts
- Application by North Lincolnshire Green Energy Park Limited for development consent.
- Original statutory deadline: 18 October 2024.
- New decision deadline set to 14 March 2025.
- Residual Waste Infrastructure Capacity Note publication expected by end of 2024.
▸