Issue Summary
This statement addresses an extension request for a statutory deadline concerning the Heckington Fen Solar Park application under the Planning Act 2008.
Action Requested
The Secretary of State has decided to extend the deadline from 9 August 2024 to no later than 27 September 2024 to allow further negotiations with landowners and to obtain necessary permissions.
Key Facts
- Ecotricity (Heck Fen) Limited submitted an application for a solar photovoltaic electricity generating station in Lincolnshire.
- The original statutory deadline was set for 9 August 2024.
- A new deadline of no later than 27 September 2024 has been established.
▸