Context
The MP references the trans-Pennine route upgrades and Huddersfield's railway station reconstruction, highlighting specific progress figures and a recent 30-day closure that caused disruption.
Question
As part of the trans-Pennine route upgrades, 25% of the route has already been electrified, with 40% due to be completed by summer 2027. Huddersfield’s famous railway station is also undergoing a £70 million reconstruction. Although there has been a 30-day closure that has led to some disruption for residents in my town, can the Secretary of State set out how the Government are ensuring the economic and social benefits of that investment will be utilised to help regenerate communities in Huddersfield?
Answer from The Secretary of State for Transport (Heidi Alexander)
I would like to acknowledge that my hon. Friend’s constituents have had to put up with some significant disruption in recent months, but I am confident that when that work is complete, Huddersfield will have a railway station fit for the future. The trans-Pennine route upgrade programme is working closely with local partners to ensure that the £11 billion of investment delivers long-term social and economic benefits for Huddersfield and local communities along the route. This includes supporting skilled jobs, improving connectivity and creating opportunities right now for local supply chains.
Was this summary accurate? Tell us
How accurate was this summary? (1 = poor, 5 = spot on)