The Minister made a statement on the publication of the report from the National Energy System Operator (NESO) following its review into the fire at the North Hyde substation, which occurred on March 20th and disrupted power supply to over 70,000 customers including Heathrow airport. He emphasised that NGET's failure to take appropriate action based on elevated moisture samples taken in 2018 was likely the cause of the fire. The Minister assured that the Government will consider NESO’s findings urgently and publish a response outlining actions to address identified issues. Additionally, he highlighted the need for improved resilience across critical infrastructure and noted ongoing initiatives such as the 10-year infrastructure strategy.