Opened the debate
The Portishead rail link is crucial due to the £300 million annual cost of congestion in the region, with traffic queueing times expected to increase by 74% by 2036. The alternative, a major new bridge, would cost at least £250 million and not be deliverable until 2030. In contrast, Portishead rail could open by 2025. Additionally, the project supports economic development, job creation, and environmental sustainability. Despite initial budget estimates of £116 million in 2017, revised forecasts indicate a need for an additional £26.82 million to cover capital and revenue costs. The right hon. Member requests the Department for Transport to provide this funding and implement governance measures to ensure the project’s success.